Santner view
August 2024
In August, the carpentry work on the first roof truss of House C was completed and work began on the second roof (House B).
was started. The rough plumbing in House C was also completed and work began on the floor structure so that the interior plastering work could begin at the end of August. Work on the brickwork of houses B and A took place and the formwork for the final reinforced concrete ceiling of house A was put in place.